Work on Indian side of Kartarpur corridor will be completed within given time frame: MHA
Sep 16, 2019
Gurdaspur (Punjab), Sep 16 (ANI): Additional Secretary of Ministry of Home Affairs, Govind Mohan inspected the Kartarpur Corridor site in Gurdaspur district on September 16 and said that Indian side of Kartarpur corridor will be completed within given time frame. Speaking to mediapersons, Govind Mohan said, “There are 3 works that are part of Indian side of the Kartarpur corridor. An extra highway of 3.5 km is being made from the Gurdaspur-Batala highway till the border point, 70% of it is done, it'll be completed by October 31. The second work is a Passenger Terminal Building (PTB) whose work is underway. In this building, there will be immigration and other facilities for the Sikh devotees who will go towards Kartarpur.”